Desenvolvimento e Acompanhamento de Projetos

Objetivos:

1. DEFINIR PROJETO E OS PRINCIPAIS CONCEITOS
2. DIFERENCIAR PROJETOS DE PRODUTOS E SERVIÇOS
3. ANALISAR A INFLUÊNCIA DOS RECURSOS HUMANOS NOS PROJETOS
4. PLANEJAR, ACOMPANHAR E CONTROLAR PROJETOS
5. IDENTIFICAR NOS PROJETOS OS ASPECTOS RELACIONADOS A MERCADO, ESCALA E LOCALIZAÇÃO
6. RECONHECER MÉTODOS E FERRAMENTAS PARA ANÁLISE ECONÔMICO-FINANCEIRA DE PROJETOS

Software: freeware Turbo Project - http://ftp.newnet.co.uk/ftp/pub/mirrors/tucows/office/adnload/173343_57191.html

Modelo para projeto de produto (adaptado do exemplo do MSProject 2003 - atenção: não revisado!!!)

New Product Development Template 766 days
Initial New Product Screening Stage 9 days
New product opportunity identified 0 days
Describe new product idea (1-page written disclosure) 2 days
Gather information required for go/no-go decision 6 days
Convene opportunity of screening committee (decision to pursue idea or not) 1 day
Decision point - go/no-go to preliminary investigation 0 days
Preliminary Investigation Stage 53 days
Assign resources to preliminary investigation 1 day
Develop preliminary investigation plan 5 days
Evaluate the market 10 days
Analyze the competition 5 days
Technical Feasibility Analysis 20 days
Produce lab scale product 10 days
Evaluate internal product 5 days
Identify production process steps required for manufacture 5 days
Assess manufacturing capabilities 10 days
Determine safety issues 10 days
Determine environmental issues 10 days
Review legal issues 10 days
Perform financial evaluation 10 days
Develop risk analysis 5 days
Draft initial development stage plan 10 days
Conduct preliminary stage review decision 2 days
Decision point - go/no-go to development stage 0 days
Development Stage 264 days
Assign resources to development stage plan 1 day
Market Evaluation 40 days
Gather market information 15 days
Identify and contact customer sample group 5 days
Perform competitor analysis 15 days
Redefine product requirements 10 days
Technical Product Evaluation 204 days
Establish product characteristics (performance criteria) 2 days
Develop prototype process 10 days
Produce prototype product 25 days
Conduct internal product review 5 days
Document patent application process 10 days
Conduct marketing/technical review 92 days
Redesign process (if necessary) 10 days
Modify prototype process 15 days
Develop plan for customer product testing 5 days
Produce product for customer evaluation 25 days
Conduct preliminary manufacturing process review 10 days
Conduct customer evaluations of prototype product 20 days
Concept Evaluation 57 days
Conduct marketing/technical review 2 days
Prepare preliminary manufacturing design 20 days
Evaluate contract manufacturing option 10 days
Review legal and patent considerations 10 days
Perform environmental review 10 days
Conduct product safety review 15 days
Perform evaluate/predict product cycle time 15 days
Update financial analysis 10 days
Risk analysis 10 days
Review preliminary investigation criteria 2 days
Develop pilot stage plan 5 days
Conduct development stage review 2 days
Decision point - go/no-go to pilot stage 0 days
Pilot Stage 115 days
Assign pilot stage resources 1 day
Secure customer commitment to participate in commercialization trials 5 days
Trial Product Manufacture 70 days
Schedule/reserve pilot production facility 5 days
Resolve raw material and finish products logistics 5 days
Review trial plan and requirements 5 days
Start trial material production 30 days
Monitor customer trials 20 days
Review preliminary trial results 10 days
Continue trial material production 30 days
Complete customer trial monitoring 20 days
Trial Analysis 49 days
Confirm sales and marketing strategies 5 days
Confirm product safety 5 days
Re-evaluate manufacturing processes 15 days
Develop commercialization plan 15 days
Review financials 5 days
Review patent and legal issues 10 days
Assign commercialization leadership responsibility and resources 2 days
Pilot stage review and commercialization decision 2 days
Commercialization Stage 195 days
Product Manufacturing and Monitoring 168 days
Confirm product specification 3 days
Confirm customer specification acceptance and trial participation 10 days
Develop manufacturing process requirements 10 days
Design and order new equipment 30 days
Install and test new equipment or equipment modifications 30 days
Confirm manufacturing capabilities 10 days
Develop and review production trial plan (resolve logistics issues) 5 days
Start production of commercial product quantities 40 days
Monitor customer acceptance testing 30 days
Commercialization Analysis 57 days
Perform internal product testing 15 days
Review production performance results 10 days
Identify long term production requirements 15 days
Recalculate product economics 10 days
Affirm decision to continue commercialization program 2 days
Post Commercialization Review 130 days
Determine if product is meeting customer cost/performance expectations 60 days
Determine if sales have met projections 60 days
Determine if product is sustaining its position against competitive response 30 days
Evaluate manufacturing process for stability and cost effectiveness 40 days
Determine if current economics are consistent with projected economics 15 days
Evaluate opportunities to expand product or product line 15 days